In some projects, there are several levels for the same floor plan.

 

This requires the engineer to work a little bit differently than usual.

 

Copy/Monitor all relevant levels as usual.

 

In this example, there is a building A(left) and building B (right)


---------------------------------------------------------------------------- 

Because what is seen in the view is controlled not only by visibility/graphic override but as well from the View range.

 

So, in many cases, the default cut height of 1200mm is too low or too high.


---------------------------------------------------------------------------- 

It is important that everything which should be connected to each floor is “drawn” / placed on the right view.

 

i.e. Spaces, which search for walls with elevation 0mm (default value, Computation Height) above placed level.


----------------------------------------------------------------------------

Here it’s important to work with several views, recommended is Work views.

 

After creating original views, create a new set of views and connect them to Fire_WorkViews template.


----------------------------------------------------------------------------

This will move all views in the Project Browser to WORK VIEWS – INITIALS.

 

Open the view template settings and exclude Fire_BrowserSub.

 

This will let the user change the value in Fire_BrowserSub on each individual view.

---------------------------------------------------------------------------- 

Move all relevant views to new subfolders, in this example A and B, because that is how the Architect defined it in their model.


---------------------------------------------------------------------------- 

“Hide” all other parts of the building in each view, so only building A is visible in views placed under subfolder A and same with B.

 

Either use Masking Regions(picture is using this method), Scope boxes, or manually update with crop region.

 

After this, start adding requirements on the different buildings.


---------------------------------------------------------------------------- 

The Views for sheets will probably not look ideal after placing all requirements in the correct building height. There will be a need to do some manual graphical fine-tuning on those views.


Note: In the right building, no doors are visible and none of the color scheme for the evacuation route as well.

---------------------------------------------------------------------------- 

Plan Regions are used to change the view range in certain parts of the floor plan. It can be found under View → Plan Views → Plan Regions


---------------------------------------------------------------------------- 

Sketch the area to cover, then change the View range in properties for that area



---------------------------------------------------------------------------- 

Now the view looks much better and finishes by going into the View template and in Annotation Categories turn off Plan Regions. Otherwise, the green border (on the right) will be visible on the prints.